NDDOT signs a contract only with a bidder that holds a North Dakota contractor license and has coverage from Workforce Safety & Insurance, so on an award your workers’ comp comes from the state and everything else comes from your own program. Getting both halves lined up before the contract reaches you for signature is what keeps the job on schedule.
Prequalification, the license and the contract are three gates
The North Dakota Department of Transportation considers proposals only from bidders it has prequalified, and it requires the prequalification statement again every year. That is a separate gate from the state license. A bidder can submit a proposal without a Secretary of State contractor license, but the department signs a contract only with one that holds the license and has secured WSI coverage. The NDDOT bid information page sets out the bidding side, and our North Dakota paving contractor insurance page covers the state rules behind it.
Workers’ comp comes only from WSI
North Dakota is a monopolistic workers’ comp state. Workforce Safety & Insurance is the sole provider, private insurers may not underwrite the coverage, and there is no self-insurance route. The statute forbids putting anyone to work in hazardous employment before applying to WSI, and a paving, sealcoating or striping business with employees falls inside that rule. WSI’s coverage requirements page explains who has to be insured. Our workers’ compensation page explains how comp fits the rest of a paving program.
The employers liability question
Because WSI writes the comp, ask what your contract expects for employers liability and how your program answers it. Some highway contracts list employers liability alongside workers’ comp. Read the provision, then have your agent confirm how that requirement is met for North Dakota work before you sign, rather than assuming the certificate that works in another state works here.
Bonds come with the bid and the award
Surety attaches at both ends. A proposal carries a bid guaranty, and the specifications call for a contract bond equal to the original contract amount. Our post on bid, performance and payment bonds explains what the surety reads before it says yes, which is worth knowing well before the award.
Liability, auto and equipment from your own program
The rest of the program is yours to buy. A North Dakota highway award usually reaches general liability, commercial auto for the haul trucks, contractors equipment for the paver, rollers and milling machine, and often an umbrella. Read the contract’s insurance provisions for every line, limit and endorsement, and send the exact wording to your agent the day the award arrives. Our post on state DOT insurance requirements explains where those requests usually stall.
Your subcontractors’ WSI status is your problem too
In North Dakota a general contractor, and any subcontractor that passed the work down, owes the premium and any penalty for the workers of a subcontractor or independent contractor that fails to secure coverage, limited to work done under that contractor. Before a striping or trucking sub starts, confirm its WSI coverage and keep the proof in the job file.
The license keeps its own insurance proof
A North Dakota contractor license comes with insurance paperwork: the applicant files a certificate of liability insurance and a WSI statement showing accepted coverage, and the Secretary of State marks the license not in good standing if the liability coverage lapses. A lapse can therefore stop a contract signing even when every other document is ready.
Where the work is
NDDOT works through district offices in cities including Fargo, Bismarck, Grand Forks, Minot, Williston and Dickinson. Keep the district office’s contact on certificate requests so they reach the people running your contract. If you are lining up an award now, request a quote for the liability side and attach the provisions. Similar steps for other state awards are in our posts on UDOT and Michigan road work.